     SECTION 1.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2012-2013.

     1.   To be expended by the department of education:

     A.   Moanalua high school, Oahu

          Design and construction of athletic field turf.

          Design                                  $300,000

          Construction                          $2,000,000

          Total funding                         $2,300,000

     B.   Moanalua high school, Oahu

          Design and construction of all-weather athletic

          track.

          Design                                  $450,000

          Construction                          $3,000,000

          Total funding                         $3,450,000


     C.   Moanalua high school, Oahu

          Design, construction, and equipment for

          performing arts center phase II.

          Design                                $4,000,000

          Construction                         $24,000,000

          Equipment                             $1,000,000

          Total funding                        $29,000,000

     D.   Moanalua middle school, Oahu

          Design and construction for air-conditioning

          expansion in buildings B and F.

          Design                                  $200,000

          Construction                          $1,000,000

          Total funding                         $1,200,000

     E.   Moanalua middle school, Oahu

          Design and construction for a new media

          technology center and renovations to existing

          computer labs; ground and site improvements;

          equipment and appurtenances.

          Design                                  $400,000

          Construction                          $4,450,000

          Equipment                               $150,000

          Total funding                         $5,000,000

     F.   Aliamanu middle school, Oahu

          Design and construction for a physical education

          running surface; ground and site improvements;

          equipment and appurtenances.

          Design                                   $20,000

          Construction                            $180,000

          Total funding                           $200,000

     G.   Moanalua elementary school, Oahu

          Design, construction, and equipment for a new

          technology center as an expansion of the library

          or new building; ground and site improvements;

          equipment and appurtenances.

          Design                                  $150,000

          Construction                          $1,970,000

          Equipment                                $30,000

          Total funding                         $2,150,000

     H.   Moanalua elementary school, Oahu

          Design and construction for parking safety

          improvements, including additional parking and

          new drop-off lane; ground and site improvements;

          equipment and appurtenances.
          Design                                   $30,000

          Construction                            $300,000

          Total funding                           $330,000

     I.   Salt Lake elementary school, Oahu

          Interior renovation and construction of

          Classroom C-1, including central air-

          conditioning, electrical upgrades, classroom

          equipment, and video and data connectivity.

          Design                                  $200,000

          Construction                            $600,000

          Equipment                               $200,000

          Total funding                         $1,000,000

     J.   Salt Lake elementary school, Oahu

          Interior renovation and construction of

          Classroom E-3, including central air-

          conditioning, electrical upgrades, classroom

          equipment, and video and data connectivity.

          Design                                  $200,000

          Construction                            $600,000

          Equipment                               $200,000

          Total funding                         $1,000,000
     K.   Salt Lake elementary school, Oahu

          Interior renovation and construction of

          Classroom E-4, including central air-

          conditioning, electrical upgrades, classroom

          equipment, and video and data connectivity.

          Design                                  $200,000

          Construction                            $600,000

          Equipment                               $200,000

          Total funding                         $1,000,000

     L.   Aliamanu elementary school, Oahu

          Design, construction, and equipment for the

          expansion of the administration building; ground

          and site improvements; equipment and

          appurtenances.

          Design                                  $400,000

          Construction                          $3,075,000

          Equipment                                $25,000

          Total funding                         $3,500,000
     M.   Aliamanu elementary school, Oahu

          Design, construction, and equipment for the expansion              of the library; ground and site improvements;                      equipment and appurtenances.

          Design                                  $500,000

          Construction                          $4,460,000

          Equipment                                $40,000

          Total funding                         $5,000,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2012.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

Capital Improvement Projects; Thirty-first Representative District Schools; Appropriation

 

Description:

Appropriates funds for capital improvement projects for schools in the Thirty-first Representative District.  Effective July 1, 2012.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.