SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2009-2010:
1. To be expended by the department of accounting and general services:
A. Roosevelt high school, Oahu
Cliff stabilization - below F bldg.
Structural bolstering to permanently stabilize a fractured and cracked cliff face that supports school buildings.
Design $ 80,000
Construction 750,000
Total funding $ 830,000
B. Roosevelt high school, Oahu
School master plan development.
Following the department of education facilities planning section recommendation that Roosevelt update the school master plan to meet school needs for the next ten years.
Plans $ 200,000
Total funding $ 200,000
C. Roosevelt high school, Oahu
Renovation and expansion of gymnasium. Renovation of existing gymnasium to comply with federal Americans with Disabilities Act regulations, improve locker room facilities, upgrade plumbing system, improve seating capacity of the gym, and a variety of essential needs to meet sports program requirements and needs.
Design $ 500,000
Construction 5,000,000
Total funding $ 5,500,000
D. Roosevelt high school, Oahu
Two hundred (200) stall multi-level parking structure.
To create additional parking for underserved faculty, staff, and students.
Design $ 90,000
Construction 810,000
Total funding $ 900,000
E. Roosevelt high school, Oahu
Implementation of cafeteria air‑conditioning upgrades.
Design $ 30,000
Construction 90,000
Total funding $ 120,000
F. Roosevelt high school, Oahu
Design and construction to replace stadium lights, plus electrical upgrades to the system.
Design $ 200,000
Construction 2,500,000
Total funding $ 2,700,000
G. Roosevelt high school, Oahu
Phase II design and construction of auditorium project.
To add the bandroom, and to create a parking and loading area in front of the school.
Plans $ 200,000
Designs 100,000
Construction 5,000,000
Total funding $ 5,300,000
H. Lincoln elementary school, Oahu
Upgrade of air-conditioning project currently underway.
Design/plans $ 500,000
Construction/labor/supplies 3,000,000
Total funding $ 3,500,000
I. Lincoln elementary school, Oahu
Repairs to rock wall in school parking lot.
Design $ 90,000
Construction 850,000
Total funding $ 940,000
J. Washington middle school, Oahu
Construction of a single-story building to serve as a parent and community center for parent meetings, gatherings, and activities.
Plans $ 10,000
Design 10,000
Construction 200,000
Equipment 25,000
Total funding $ 245,000
K. Washington intermediate school, Oahu
Construction of new elevator for H bldg. to make science labs and art classrooms available to wheelchair students.
Plans $ 10,000
Design 10,000
Construction 150,000
Equipment 25,000
Total funding $ 195,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2009.
INTRODUCED BY: |
_____________________________ |
|
|