     SECTION 1.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2013-2014.

     1.   To be expended by the department of education:

     A.   Aiea elementary school, Oahu

          Design and construction for campus-wide air conditioning; ground and site improvements; and equipment and appurtenances.

          Design                                       $300,000

          Construction                               $1,200,000

          Total funding                              $1,500,000

     B.   Aiea elementary school, Oahu

          Design, construction, and equipment for a science, technology, engineering, and math center; ground and site improvements; and equipment and appurtenances.

          Design                                       $350,000

          Construction                               $3,170,000

          Equipment                                     $30,000

          Total funding                              $3,550,000

     C.   Aiea high school, Oahu

          Design, construction, and equipment for a weight training facility; ground and site improvements; and equipment and appurtenances.

          Design                                       $160,000

          Construction                               $1,230,000

          Equipment                                     $10,000

          Total funding                              $1,400,000

     D.   Aiea high school, Oahu

          Design, construction, and equipment to replace football field and track with synthetic surface system; ground and site improvements; and equipment and appurtenances.

          Design                                       $499,000

          Construction                               $4,500,000

          Equipment                                      $1,000

          Total funding                              $5,000,000

     E.   Aiea intermediate school, Oahu

          Design, construction, and equipment for improvements to cafeteria stage and support spaces; ground and site improvements; and equipment and appurtenances.

          Design                                        $50,000

          Construction                                 $500,000

          Equipment                                     $10,000

          Total funding                                $560,000

     F.   Aiea intermediate school, Oahu

          Design and construction for a retaining wall, perimeter fencing and gates; ground and site improvements; and equipment and appurtenances.

          Design                                       $100,000

          Construction                                 $900,000

          Total funding                              $1,000,000

     G.   Aiea intermediate school, Oahu

          Design, construction, and equipment for an applied technology center; ground and site improvements; and equipment and appurtenances.

          Design                                       $200,000

          Construction                               $1,670,000

          Equipment                                     $30,000

          Total funding                              $1,900,000

     H.   Alvah Scott elementary school, Oahu

          Design and construction for traffic safety improvements and parking expansion; ground and site improvements; and equipment and appurtenances.

          Design                                        $75,000

          Construction                                 $650,000

          Total funding                                $725,000

     I.   Highlands intermediate school, Oahu

          Design and construction of a chain link fence on top of existing rock wall surrounding the school.

          Design                                        $20,000

          Construction                                 $160,000

          Total funding                                $180,000

     J.   Highlands intermediate school, Oahu

          Design and construction of an addition to the existing rock wall surrounding the school.

          Design                                        $25,000

          Construction                                 $250,000

          Total funding                                $275,000

     K.   Kanoelani elementary school, Oahu

          Design and construction of a ten foot fence between the school campus and the adjacent community park.

          Design                                         $1,000

          Construction                                 $249,000

          Total funding                                $250,000

     L.   Kanoelani elementary school, Oahu

          Design and construction of a portable classroom to serve as the school's music classroom.

          Design                                         $1,000

          Construction                                 $299,000

          Total funding                                $300,000

     M.   Kanoelani elementary school, Oahu

          Design and installation of school-wide air conditioning.

          Design                                         $1,000

          Construction                                 $449,000

          Total funding                                $450,000

     N.   Manana elementary school, Oahu

          Design and construction for five additional classrooms.

          Design                                       $200,000

          Construction                               $1,800,000

          Total funding                              $2,000,000

     O.   Momilani elementary school, Oahu

          Design and construction of campus-wide electrical upgrades.

          Design                                       $100,000

          Construction                                 $500,000

          Total funding                                $600,000

     P.   Palisades elementary school, Oahu

          Design and construction for ten additional parking spaces below the main parking lot and a retaining wall.

          Design                                       $100,000

          Construction                               $1,000,000

          Total funding                              $1,100,000

     Q.   Pearl Ridge elementary school, Oahu

          Design and construction for covered walkways to the cafeteria from buildings H and J and the administration building; ground and site improvements; and equipment and appurtenances.

          Design                                       $100,000

          Construction                                 $900,000

          Total funding                              $1,000,000

     R.   Pearl City elementary school, Oahu

          Design and construction for campus-wide electrical upgrade.

          Design                                       $225,000

          Construction                               $1,775,000

          Total funding                              $2,000,000

     S.   Pearl City Highlands elementary school, Oahu

          Design and construction of an extension of the administrative building.

          Design                                        $50,000

          Construction                                 $500,000

          Total funding                                $550,000

     T.   Pearl City high school, Oahu

          Design, construction, and equipment to replace football field and track with synthetic surface system; ground and site improvements; and equipment and appurtenances.

          Design                                       $500,000

          Construction                               $4,000,000

          Equipment                                    $500,000

          Total funding                              $5,000,000

     U.   Waiau elementary school, Oahu

          Design and construction for air conditioning of ten portable classrooms.

          Design                                        $20,000

          Construction                                  $80,000

          Total funding                                $100,000

     V.   Waiau elementary school, Oahu

          Design and construction of campus-wide electrical upgrades.

          Design                                        $35,000

          Construction                                 $400,000

          Total funding                                $435,000

     W.   Waimalu elementary school, Oahu

          Design and construction for elevator to second floor and connection to buildings D and E; ground and site improvements; and equipment and appurtenances.

          Design                                       $120,000

          Construction                               $1,130,000

          Total funding                              $1,250,000

     X.   Webling elementary school, Oahu

          Design and construction for campus-wide electrical upgrades; ground and site improvements; and equipment and appurtenances.

          Design                                       $200,000

          Construction                               $1,499,000

          Equipment                                      $1,000

          Total funding                              $1,700,000

     2.   To be expended by the university of Hawaii:

     A.   Leeward community college, Oahu

          Construction of upgrades to the theatre

          Construction                               $7,500,000

          Total funding                              $7,500,000

     B.   Leeward community college, Oahu

          Planning and design of a Native Hawaiian center for excellence.

          Planning                                     $       

          Design                                       $       

          Total funding                              $2,000,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the department of education for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2013.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

Capital Improvement Projects; Schools of the Thirty-third, Thirty-fourth, and Thirty-fifth Representative Districts

 

Description:

Appropriates funds for capital improvement projects for schools in the thirty-third, thirty-fourth, and thirty-fifth representative districts.  Effective July 1, 2013.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.