HOUSE OF REPRESENTATIVES |
H.B. NO. |
350 |
TWENTY-EIGHTH LEGISLATURE, 2015 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE THIRTY-THIRD, THIRTY-FOURTH, AND THIRTY-FIFTH REPRESENTATIVE DISTRICTS.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $57,285,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2015-2016 for the purpose of financing capital improvement projects for the thirty-third, thirty-fourth, and thirty-fifth representative districts, as follows:
1. To be expended by the department of education:
A. Aiea elementary school, Oahu
Design and construction for completion of campus-wide heat/noise abatement; ground and site improvements; equipment and appurtenances.
Design $ 300,000
Construction 2,700,000
Total funding $ 3,000,000
B. Aiea elementary school, Oahu
Design, construction, and equipment for demolition of building H and replacement with a STEM center; ground and site improvements; equipment and appurtenances.
Design $ 670,000
Construction 4,000,000
Equipment 30,000
Total funding $ 4,700,000
C. Aiea intermediate school, Oahu
Design, construction, and equipment for expansion of band room; ground and site improvements; equipment and appurtenances.
Design $ 475,000
Construction 1,500,000
Equipment 25,000
Total funding $ 2,000,000
D. Aiea intermediate school, Oahu
Design, construction, and equipment for an applied technology center; ground and site improvements; equipment and appurtenances.
Design $ 500,000
Construction 2,900,000
Equipment 100,000
Total funding $ 3,500,000
E. Aiea high school, Oahu
Design and construction for air conditioning of building F; ground and site improvements; equipment and appurtenances.
Design $ 300,000
Construction 1,700,000
Total funding $ 2,000,000
F. Alvah Scott elementary school, Oahu
Design and construction for campus-wide electrical upgrade; ground and site improvements; equipment and appurtenances.
Design $ 250,000
Construction 1,500,000
Total funding $ 1,750,000
G. Highlands intermediate school, Oahu
Design and construction for air conditioning of building G; ground and site improvements; equipment and appurtenances.
Design $ 100,000
Construction 450,000
Total funding $ 550,000
H. Highlands intermediate school, Oahu
Design and construction for air conditioning of building K; ground and site improvements; equipment and appurtenances.
Design $ 100,000
Construction 450,000
Total funding $ 550,000
I. Momilani elementary school, Oahu
Design and construction of a storage shed by the electrical room; ground and site improvements; equipment and appurtenances.
Design $ 40,000
Construction 160,000
Total funding $ 200,000
J. Momilani elementary school, Oahu
Design and construction of a covered play court; ground and site improvements; equipment and appurtenances.
Design $ 350,000
Construction 2,400,000
Total funding $ 2,750,000
K. Palisades elementary school, Oahu
Design and construction for parking expansion and a retaining wall; ground and site improvements; equipment and appurtenances.
Design $ 100,000
Construction 1,000,000
Total funding $ 1,100,000
L. Pearl City elementary school, Oahu
Design and construction of electrical upgrades for ten classroom buildings.
Design $ 200,000
Construction 1,800,000
Total funding $ 2,000,000
M. Pearl City elementary school, Oahu
Removal and construction of interior ceiling in cafeteria.
Removal $ 40,000
Construction 160,000
Total funding $ 200,000
N. Pearl City elementary school, Oahu
Installation of gutters on single side of eight classroom buildings.
Installation $ 50,000
Total funding $ 50,000
O. Pearl City high school, Oahu
Design and construction to concrete upper courtyard by buildings B and C; ground and site improvements; equipment and appurtenances.
Design $ 40,000
Construction 130,000
Total funding $ 170,000
P. Pearl City high school, Oahu
Design and construction of handicap parking lot by tennis court; ground and site improvements; equipment and appurtenances.
Design $ 50,000
Construction 200,000
Total funding $ 250,000
Q. Pearl City Highlands elementary school, Oahu
Design, construction, and equipment for new administration building; ground and site improvements; equipment and appurtenances.
Design $ 1,420,000
Construction 16,000,000
Equipment 80,000
Total funding $17,500,000
R. Pearl Ridge elementary school, Oahu
Design and construction for air conditioning of buildings H and J; ground and site improvements; equipment and appurtenances.
Design $ 325,000
Construction 2,155,000
Total funding $ 2,480,000
S. Waiau elementary school, Oahu
Design and construction of a covered walkway; ground and site improvements; equipment and appurtenances.
Design $ 50,000
Construction 350,000
Total funding $ 400,000
T. Waiau elementary school, Oahu
Design and construction for air conditioning of ten portable classrooms; ground and site improvements; equipment and appurtenances.
Design $ 20,000
Construction 80,000
Total funding $ 100,000
U. Waiau elementary school, Oahu
Design and construction of two playgrounds.
Design $ 40,000
Construction 160,000
Total funding $ 200,000
V. Waimalu elementary school, Oahu
Design and construction for campus-wide electrical upgrade; ground and site improvements; equipment and appurtenances.
Design $ 250,000
Construction 1,500,000
Total funding $ 1,750,000
W. Webling elementary school, Oahu
Design and construction for campus-wide electrical upgrade; ground and site improvements; equipment and appurtenances.
Design $ 250,000
Construction 1,500,000
Total funding $ 1,750,000
X. Webling elementary school, Oahu
Design, construction, and equipment for new and/or expansion of support facilities; ground and site improvements; equipment and appurtenances.
Design $ 800,000
Construction 6,650,000
Equipment 50,000
Total funding $ 7,500,000
2. To be expended by the department of transportation:
A. H-1 freeway near Ulune street, Oahu
Design and construction a noise barrier along the H-1 freeway near Ulune street to provide traffic noise reduction.
Design $ 10,000
Construction 825,000
Total funding $ 835,000
SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2018, shall lapse as of that date.
SECTION 3. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 4. This Act shall take effect on July 1, 2015.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 33rd, 34th, and 35th Representative Districts
Description:
Authorizes issuance of general obligation bonds and appropriates funds for capital improvement projects in the 33rd, 34th, and 35th representative districts.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.