HOUSE OF REPRESENTATIVES

H.B. NO.

1372

THIRTIETH LEGISLATURE, 2019

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of the thirteenth representative district.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $120,749,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2019-2020 for the purpose of financing capital improvement projects for the thirteenth representative district, as follows:

1.   To be expended by the department of education:

A.   Haiku elementary school, Maui

     Plans, design, and construction for covered walkways; roof.

Plans                                 $    50,000

Design                                $    50,000

Construction                          $   500,000

     Total funding                    $   600,000

B.   Hana school, Maui

     Plans and construction for roof replacement; exterior improvements.

Plans                                 $    50,000

Construction                          $   760,000

     Total funding                    $   810,000

C.   Kaunakakai school, Molokai

     Plans and construction for new bleachers.

Plans                                 $    10,000

Construction                          $   240,000

     Total funding                    $   250,000

D.   Kaunakakai school, Molokai

     Plans, design, and construction for new roof.

Plans                                 $    10,000

Design                                $    10,000

Construction                          $   480,000

     Total funding                    $   500,000

E.   Kilohana school, Molokai

     Plans and construction for electrical upgrade.

Plans                                 $    10,000

Construction                          $   140,000

     Total funding                    $   150,000

F.   Kilohana school, Molokai

     Plans, installation, and equipment for air conditioning units in four classrooms.

Plans                                 $     5,000

Installation/Equipment                $    50,000

     Total funding                    $    55,000

G.   Kualapuu school, Molokai

     Plans, design, installation, and equipment for new playground.

Plans                                 $    10,000

Design                                $    10,000

Installation/Equipment                $   165,000

     Total funding                    $   185,000

H.   Kualapuu school, Molokai

     Equipment and installation for solar panels.

Equipment                             $   400,000

Installation                          $   150,000

     Total funding                    $   550,000

I.   Lanai high school, Lanai

     Design and construction for new roof.

Design                                $    50,000

Construction                          $   450,000

     Total funding                    $   500,000

J.   Molokai middle school, Molokai

     Plans, design, and construction for exterior renovation.

Plans                                 $     1,000

Design                                $     1,000

Construction                          $    66,000

     Total funding                    $    68,000

K.   Molokai middle school, Molokai

     Plans, design, and construction for roof replacement.

Plans                                 $    10,000

Design                                $    10,000

Construction                          $   160,000

     Total funding                    $   180,000

L.   Molokai high school, Molokai

     Plans, design, and construction for upgraded electrical work and rewire; resurfacing; re-roofing walkways; replacing gutters; renovating showers; other improvements.

Plans/Design                          $    33,000

Construction                          $   250,000

     Total funding                    $   283,000

M.   Paia elementary school, Maui

     Plans, design, and construction for six classrooms.

Plans                                 $   500,000

Design                                $   500,000

Construction                          $29,000,000

     Total funding                    $30,000,000

2.   To be expended by the department of land and natural resources:

A.   Manele small boat harbor, Lanai

     Plans, design, construction, and equipment for fishing hoist.

Plans                                 $     1,000

Design                                $     1,000

Construction                          $     1,000

Equipment                             $    75,000

     Total funding                    $    78,000

3.   To be expended by the department of transportation airports division:

A.   Hana airport, Maui

     Design and construction for airport improvement project.

Design                                $ 1,000,000

Construction                          $15,850,000

     Total funding                    $16,850,000

B.   Molokai airport, Molokai

     Design for electrical upgrades.

Design                                $   150,000

     Total funding                    $   150,000

4.   To be expended by the department of transportation harbors division:

A.   Hana harbor, Maui

     Design and construction of improvements to remove the Hana pier superstructure.

Design                                $   200,000

Construction                          $ 3,500,000

     Total funding                    $ 3,700,000

5.   To be expended by the department of transportation highways division:

A.   Haleakala highway, Maui

     Land, design, and construction for intersection improvements, Makawao avenue.

Land                                  $     1,000

Design                                $     1,000

Construction                          $ 5,748,000

     Total funding                    $ 5,750,000

B.   Hana highway, Maui

     Plans for bridge preservation.

Plans                                 $ 1,280,000

     Total funding                    $ 1,280,000

C.   Hana highway, Maui

     Design and construction for drainage improvements.

Design                                $    80,000

Construction                          $ 1,200,000

     Total funding                    $ 1,280,000

D.   Hana highway, Maui

     Plans, design, and construction for emergency repairs and improvements.

Plans                                 $   100,000

Design                                $   100,000

Construction                          $19,800,000

     Total funding                    $20,000,000

E.   Hana highway, Maui

     Design and construction for guardrails.

Design                                $     1,000

Construction                          $ 3,999,000

     Total funding                    $ 4,000,000

F.   Hana highway, Maui

     Design and construction for improvements, Huelo to Hana.

Design                                $   100,000

Construction                          $ 3,300,000

     Total funding                    $ 3,400,000

G.   Hana highway, Maui

     Design for Kailua stream bridge.

Design                                $   600,000

     Total funding                    $   600,000

H.   Hana highway, Maui

     Land and design for Kopiliula stream bridge.

Land                                  $   235,000

Design                                $   870,000

     Total funding                    $ 1,105,000

 

I.   Hana highway, Maui

     Design for Makanali stream bridge.

Design                                $   615,000

     Total funding                    $   615,000

J.   Hana highway, Maui

     Land, design, and construction for improvements, milepost 28.1.

Land                                  $    50,000

Design                                $   105,000

Construction                          $   675,000

     Total funding                    $   830,000

K.   Hana highway, Maui

     Land and design for Mokulehua stream bridge.

Land                                  $   200,000

Design                                $   800,000

     Total funding                    $ 1,000,000

L.   Hana highway, Maui

     Plans, design, and construction for pedestrian safety mitigation, Pilialoha street.

Plans                                 $     1,000

Design                                $     1,000

Construction                          $   248,000

     Total funding                    $   250,000

M.   Hana highway, Maui

     Land and design for Puohokamoa stream bridge.

Land                                  $   180,000

Design                                $   730,000

     Total funding                    $   910,000

N.   Hana highway, Maui

     Plans, design, and construction for rockfall mitigation.

Plans                                 $   265,000

Design                                $   735,000

Construction                          $12,132,000

     Total funding                    $13,132,000

O.   Hana highway, Maui

     Design and construction for improvements, Uakea road.

Design                                $   160,000

Construction                          $ 3,055,000

     Total funding                    $ 3,215,000

P.   Hana highway, Maui

     Land and design for Ulaino stream bridge.

Land                                  $   195,000

Design                                $   755,000

     Total funding                    $   950,000

Q.   Kamehameha V highway, Molokai

     Land, design, and construction for drainage improvements.

Land                                  $    50,000

Design                                $    40,000

Construction                          $   900,000

     Total funding                    $   990,000

R.   State highways, Molokai

     Design and construction for guardrail and shoulder improvements.

Design                                $   333,000

Construction                          $ 6,100,000

     Total funding                    $ 6,433,000

6.   To be expended by the county of Maui:

A.   Equipment for emergency response.

Equipment                             $   100,000

     Total funding                    $   100,000

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2022, shall lapse as of that date.

     SECTION 3.  The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended by the designated expending agencies for the purposes of this Act.

     SECTION 4.  This Act shall take effect on July 1, 2019.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; 13th Representative District; GO Bonds; Appropriation

 

Description:

Authorizes issuance of general obligation bonds and appropriates funds for capital improvement projects for the 13th Representative District.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.