     SECTION 1.  The legislature finds that, founded in 1930 and situated in Makiki on the island of Oahu, President Theodore Roosevelt high school has grown to serve an enrollment of more than one thousand four hundred students.  The school's existing gymnasium and music building were constructed over fifty years ago and do not meet current department of education standards.

     The legislature provided funding for plans and design for a master plan for a new gymnasium, new music building, and additional on-site parking in Act 106, Session Laws of Hawaii 2012.  The final master plan, DOE Job No. Q22000-13, dated December 23, 2014, presented the preferred master plan for:

     (1)  A new gymnasium over a one-level parking structure at the site of the existing gymnasium; and

     (2)  A new two-story music building and repurposing of the existing music building.

     The purpose of this Act is to provide funding for the implementation of the master plan for the new music facilities for President Theodore Roosevelt high school.

     SECTION 2.  The director of finance is authorized to issue general obligation bonds in the sum of $9,850,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2019-2020 for the purpose of financing capital improvement projects as follows:

          President Theodore Roosevelt high school

Plans, design, construction, and equipment for new music facilities with classrooms, practice rooms, teacher offices, and other related facilities; ground and site improvements; and appurtenances.

          Plans                                    $250,000

          Design                                 $1,500,000

          Construction                           $7,600,000

          Equipment                                $500,000

          Total funding                          $9,850,000

     SECTION 3.  The sum appropriated for the capital improvement projects set forth in section 2 of this Act shall be expended by the department of education for the purposes of this Act.

     SECTION 4.  The appropriation made for the capital improvement project authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2022, shall lapse as of that date.

     SECTION 5.  This Act shall take effect on July 1, 2019.

 

INTRODUCED BY:

_____________________________

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 


 

Report Title:

Capital Improvement Projects; CIP; GO Bonds; President Roosevelt High School; Music Facilities; Appropriation

 

Description:

Authorizes issuance of GO bonds to finance plans, design, construction, and equipment for new music facilities at President Roosevelt high school.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.