     SECTION 1.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2019-2020:

     1.   To be expended by the department of education:

     A.   Kanoelani elementary school, Oahu

Plans and construction to expand the cafeteria; and ground and site improvements.

          Plans                                    $150,000

          Construction                           $2,850,000

          Total funding                          $3,000,000

     B.   Mililani high school, Oahu

          Plans, design, and construction for a new gymnasium building and to refurbish the current gymnasium into a performing arts facility.

          Plans                                    $150,000

          Design                                   $250,000

          Construction                          $28,600,000

          Total                                 $29,000,000

C.   Mililani middle school, Oahu

          Plans, design, construction, and equipment to widen the sidewalks campus-wide; ground and site improvements; and equipment and appurtenances.

          Plans                                     $1,000

          Design                                    $1,000

          Construction                             $497,000

          Equipment                                  $1,000

          Total                                    $500,000

     D.   Mililani middle school, Oahu

          Plans, design, construction, and equipment to waterproof the walls of the covered playcourt and improve the drainage for building F; ground and site improvements; and equipment and appurtenances.

          Plans                                     $1,000

          Design                                    $1,000

          Construction                             $247,000

          Equipment                                  $1,000

          Total                                    $250,000

     E.   Mililani middle school, Oahu

          Plans, design, construction, and equipment to replace the flooring in portable classrooms one, two, three, and four; ground and site improvements; and equipment and appurtenances.

          Plans                                     $1,000

          Design                                    $1,000

          Construction                              $37,000

          Equipment                                  $1,000

          Total                                     $40,000

     F.   Mililani middle school, Oahu

          Plans, design, construction, and equipment to resurface the bus lane and campus access road; ground and site improvements; and equipment and appurtenances.

          Plans                                     $1,000

          Design                                    $1,000

          Construction                             $647,000

          Equipment                                  $1,000

          Total                                    $650,000

     G.   Mililani Uka elementary school, Oahu

          Design and construction to stabilize an undeveloped eroding slope fronting the Kamehameha highway side of the campus; and ground and site improvements.

          Design                                   $200,000

          Construction                           $1,000,000

          Total                                  $1,200,000

     H.   Mililani Waena elementary school, Oahu

          Design and construction to expand the administration building; and ground and site improvements.

          Design                                   $500,000

          Construction                           $2,250,000

          Total                                  $2,750,000

     I.   Pearl City high school, Oahu

Design and construction for campus-wide electrical upgrades; and ground and site improvements.

          Design                                 $1,000,000

          Construction                          $10,000,000

          Total funding                         $11,000,000

     J.   Pearl City high school, Oahu

Design, construction, and equipment to replace the bleacher system in the gymnasium; ground and site improvements; and equipment and appurtenances.

          Design                                   $200,000

          Construction                             $500,000

          Equipment                              $1,500,000

          Total funding                          $2,200,000

     K.   Pearl City high school, Oahu

Design and construction to build restroom facilities at the baseball and softball fields; ground and site improvements; and equipment and appurtenances.

          Design                                   $500,000

          Construction                           $5,000,000

          Total funding                          $5,500,000

     L.   Pearl City high school, Oahu

Design and construction to resurface the tennis courts; and ground and site improvements.

          Design                                   $200,000

          Construction                           $2,000,000

          Total funding                          $2,200,000

     M.   Waikele elementary school, Oahu

          Plans and design for an innovation center.

          Plans                                    $150,000

          Design                                   $150,000

          Total                                    $300,000

     N.   Waipahu high school, Oahu

Construction for phase two of a new integrated academic classroom building; and ground and site improvements.

          Construction                          $15,500,000

          Total funding                         $15,500,000

     O.   Waipahu high school, Oahu

Design and construction to re-key the locks on the exterior doors campus-wide.

          Design                                    $30,000

          Construction                             $165,000

          Total funding                            $195,000

     P.   Waipahu high school, Oahu

Construction for phase two of the campus-wide exterior painting of buildings.

          Construction                             $380,000

          Total funding                            $380,000

     Q.   Waipahu intermediate school, Oahu

Design and construction to complete a new DREAMS building for digital, media, engineering, animation, music, and science classes; and ground and site improvements.

          Design                                   $350,000

          Construction                          $24,650,000

          Total funding                         $25,000,000

     R.   Waipahu intermediate school, Oahu

Design for the development and improvement of the lower campus.

          Design                                   $250,000

          Total funding                            $250,000

     2.   To be expended by the university of Hawaii:

     A.   Leeward community college, Oahu

Design and construction for fascia and sidewalk repairs.

          Design                                   $700,000

          Construction                           $7,300,000

          Total funding                          $8,000,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2019.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; 37th Representative District

 

Description:

Appropriates funds for capital improvement projects for the benefit of the 37th Representative District.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.