HOUSE OF REPRESENTATIVES

H.B. NO.

701

THIRTY-FIRST LEGISLATURE, 2021

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirty-fifth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $67,001,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2021-2022 for the purpose of capital improvement projects for the thirty-fifth representative district, as follows:

1.   Lehua elementary school, Oahu

     Land, construction, and equipment for new administration and library building.

     Land                             $1,000

     Construction                $10,000,000

     Equipment                      $200,000

          Total funding                    $10,201,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Pearl City elementary school, Oahu

     Plans, design, and construction for campus-wide electrical upgrade.

     Plans                           $60,000

     Design                          $75,000

     Construction                 $2,365,000

          Total funding                     $2,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Pearl City high school, Oahu

     Design, construction, and equipment for bleacher replacement.

     Design                         $100,000

     Construction                   $250,000

     Equipment                      $600,000

          Total funding                       $950,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Pearl City high school, Oahu

     Design, construction, and equipment for medical classroom renovation.

     Design                         $100,000

     Construction                 $1,000,000

     Equipment                      $500,000

          Total funding                     $1,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Pearl City high school, Oahu

     Design and construction for tennis court resurfacing.

     Design                          $50,000

     Construction                   $600,000

          Total funding                       $650,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Pearl City high school, Oahu

     Design, construction, and equipment for construction of an outdoor stage and gathering area.

     Design                          $50,000

     Construction                   $175,000

     Equipment                       $25,000

          Total funding                       $250,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Waipahu high school, Oahu

     Construction for phase two of a new integrated academic classroom building.

     Construction                $20,000,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Waipahu high school, Oahu

     Construction for new portables for department of education's adult education administration offices.

     Construction                 $3,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Waipahu high school, Oahu

     Design and construction for re-keying of all locks on exterior doors throughout campus.

     Design                          $75,000

     Construction                   $275,000

          Total funding                       $350,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Waipahu high school, Oahu

     Construction for phase two of campus-wide exterior painting of buildings.

     Construction                   $500,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Waipahu intermediate school, Oahu

     Construction for completion of DREAMS building.

     Construction                $27,000,000

          Total funding                    $27,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2021.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Thirty-fifth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirty-fifth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.